永峻工程顧問股份有限公司 | 長輝工程顧問股份有限公司

Shin Kong Mitsukoshi, Xinyi Place, A9

Taipei City

2002

HCCH & Associates Architects Planners & Engineers

  • Stories
    9F+B5
  • Altitude
    45.8 m
  • Construction type
    SS
  • Structural system
    SMRF
  • Usage
    Retail
To retain the head of the retail market in the Hsin-Yi District, the owner invested this project as the third branch of the department store series.  To meet the fast changes of the retail market, the numbers and the scales of the design changed during the design and construction phases were numerous.  These evaluations and modifications were hard issues beyond the professional concern.
 
The deep excavation and the water uplift problem were major concerns of the foundation design for this project.  Several buttress walls underneath the basement were utilized as combined foundation system.  These buttress walls settled the differential settlement and water uplift problem.  The displacements of the slurry walls during excavation were also reduced by these additional buttress walls.
 
Reset map